Instrumentation turnaround spares — 400 kbpd refinery, Eastern Province

Single-shipment turnaround spares package for a 400 kbpd refinery in the Eastern Province of Saudi Arabia, supporting a scheduled major maintenance shutdown.

Our role
Lead supplier — full turnaround instrumentation and control-valve package, including SABER conformity.
The challenge

What we walked into.

A 6-week turnaround required ~1,200 unique instrumentation and valve SKUs landed at a single inspection point three weeks before turnaround start. Mixed long-lead items and SABER conformity needed.
Approach

How we delivered.

  1. 01Built a single consolidated BoM from the turnaround engineering package — 1,243 line items across 17 process units.
  2. 02Negotiated factory inspection slots with 8 manufacturers; conducted parallel third-party inspection through SGS at origin.
  3. 03Coordinated SABER conformity declarations and SASO certificates of conformity for the entire shipment.
  4. 04Delivered as 14 sea containers consolidated through King Abdulaziz Port (Dammam) on a fixed-date window.
Outcome

What changed.

99.6% line-item accuracy at receipt.
All 1,243 SKUs landed within the contracted 3-week pre-turnaround window.
Zero customs delays — every container cleared in under 48 hours.
Technologies & equipment
Pressure, temperature, flow and level transmitters
Control valves, on-off valves, safety valves
Hazardous-area motors, drives, junction boxes