Cement plant motor and drive upgrade — Jordan — The Power Contractor case study
Manufacturing · 🇯🇴 Jordan · 2023

Cement plant motor and drive upgrade — Jordan

A two-phase motor and variable-frequency drive replacement programme across a cement plant near Amman, targeting energy-efficiency gains and reliability improvements.

Our role
Motor and drive supplier; commissioning support.
The challenge

What we walked into.

Legacy motors averaging 22 years in service. Repeated bearing failures on key kiln and mill positions. No drives on key high-inertia loads — high start-up current causing utility issues.
Approach

How we delivered.

  1. 01Engineering audit across all 120 motor positions — sized current load, condition, and replacement priority.
  2. 02Phased replacement: 40 motors per 4-month tranche, prioritising kiln, raw mill and coal mill.
  3. 03Added VFDs on 18 key high-inertia loads.
  4. 04Trained the maintenance team on commissioning and standard parameter sets.
Outcome

What changed.

14% reduction in motor-related electricity consumption.
Bearing-related failures down ~80% on replaced positions.
Start-up current on critical mills reduced 65% with VFD addition.
Technologies & equipment
IE3 and IE4 efficiency-class three-phase motors (low voltage and medium voltage)
Variable frequency drives (LV and MV)
Soft starters